| Activity | Unit | Total Qty | Completed This Period | Cumulative Completed | % Complete | |----------|------|-----------|----------------------|----------------------|-------------| | Drain pipe installation (floor 2–3) | LF | 1,800 | 400 | 1,600 | 89% | | Water supply piping (floor 4) | LF | 1,200 | 0 | 700 | 58% | | Sprinkler head installation (floor 1) | No. | 150 | 150 | 150 | 100% | | Stack riser installation (core) | Floor | 12 | 2 | 6 | 50% |
To ensure clarity for project leads and clients, a detailed report should be structured with the following key elements: